Prime Equipment Solutions Cuts Flush Water by 80%
Prime Equipment Solutions cuts commissioning water use by about 80% with closed-loop RO filtration for data center systems.

Prime Equipment Solutions has grown from roughly 13 to 52 employees in six months as it expands its mechanical readiness work for data centers and other mission-critical facilities. The Abilene, Texas, company is on track to reach 100 employees and has launched a new website built around its patent-pending closed-loop reverse osmosis filtration process. The process reduces water use during system flushing by about 80% and cuts flush time roughly in half. The announcement comes as Texas agencies audit data center water and power consumption, while the Texas Commission on Environmental Quality has paused data center permits with no set end date.
Closed Loop Flushing Process
Rather than using repeated drain-and-refill cycles, Prime’s closed-loop RO units connect directly to a system and circulate water through progressive filtration until conductivity, dissolved solids and clarity reach target levels. Post-flush circulation and filtration continue through fill and startup, with each stage documented for the owner’s turnover package.
Dillon Rodgers, CEO at Prime Equipment Solutions, said:
“Everyone's talking about how much water a data center uses once it's running. Almost nobody's talking about the water it takes to get one ready. Every cooling loop has to be filled, flushed, tested and cleaned before a single server goes live. The old way is to drain it, dump it, refill it, repeat. Our closed-loop process cleans the water in place. It's faster for the schedule, and in a state asking hard questions about water, it's the responsible way to build.”
Team Growth In West Texas
Prime’s expansion follows a period of rising competition for skilled labor. In the 2026 AGC–NCCER Workforce Survey, 58% of firms doing data center work said those projects increased competition for skilled workers.
Denham McCollum, COO at Prime Equipment Solutions, said:
“We went from 13 people to 52 because the work demanded it, and we're not slowing down. Flushing, testing and commissioning happen at the very end of a build, when there's no slack left in the schedule. GCs need a team that can show up with crews and equipment. That's what we're building in West Texas.”
Mechanical Readiness Services
The company provides mechanical flushing and filtration, including closed-loop RO fluid remediation, along with post-flush circulation and filtration, hydrostatic testing, false heat load generation for chiller commissioning, glycol injection and storage, freeze protection circulation, and water sourcing, storage and trucking. Prime currently supports projects in Texas, Montana, Wyoming, Arizona and Louisiana.
The new site provides contractors and owners with a route to request a quote, access The Readiness Report field guide, and view openings for field technicians, operators and engineers.